Implementation of routine maintenance, preventive and emergency via Jerash/Ajloun Road And Irbid/Ajloun Road and zarqaa/jerash Road,Total length (100) km.
Implementation of routine maintenance, preventive and emergency via Irbid /North Shouneh / Ardah Road,Total length (80km)
.....
The project includes the establishment of the intersection of multi-level (( 4 levels)) at the junction of Airport Road with a Marj Al-Hammam / Street Arafat road. The project includes the construction of a road with six lanes which is approximately 1.6 km long. This includes; upper bridge 270 m length and two tunnels under the airport road with entry and exit lanes in addition it is required to re-create almost 1.3 km from "the airport road. Moreover the work also includes the establishment of the necessary protections phrases and providing the required road signs with the required traffic safety and lighting works/drainage/and rainwater network construction. The Project construction work includes cut and fill work together with constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses. Furthermore the project includes concrete works that is required for the curvets, box curvets/pavements and other miscellaneous work like elements of safety and road painting
Implementation of routine maintenance, preventive and emergency via Amman Salt Al-Kamalya roundabout to Zay Al-Arda South Shouna bridge until the intersection with the road Naour Dead Sea in addition to the path of Salt / Wadi Shuaib, total length (( 100)) km.
The project consist of the road re-construction completion and maintenance of North Shouneh-South Shouneh road for the part extending from Deir Alla to Kofranjah Intersection. The existing 2 lanes section of the road with a total length of approximately 7.0kms will be widened to accommodate a four lanes divided highway. The Works also include elements of safety (signs/ painting) providing rainwater drainage / providing electrical network / Sewage water concrete storage tanks.
Asphalt work in various regions for Ministry of public works & housing. Work included removing existing asphalt and disposing it together with constructing road layers which includes binder/wearing courses.
Construction a four carriageway road with length of five kilometer. The project work consisted of providing infrastructure for the area including “providing water network , electricity networking including sewage storing zones, constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses / pavements (curbstone) / Drainage / Box curvets / and Elements of traffic safety”
Earthwork for the construction of the treatment plant. Also the work included the development of roads nearby the treatment works
The project consists of the construction of new roadway portion (Road 8) in “King Hussein Bin Talal Development zone” with total length of 950m. The Project also includes; construction of 2 Major roundabouts / Sidewalk / Median / Milling of existing asphalt / All earthwork necessary including structural excavation and backfill slope cutting / constructing all road layers (Topping, Sub base, Base, Wearing, Binder) / Construction of miscellaneous related work including protection , drainage, box curvets, retaining walls installation of new guardrail, curb stone, road signs and pavement marking
The Project consisted of constructing a five kilometer length two carriageway road. Work includes cut and fill work together with constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses.
Asphalt work in various regions for Greater Amman Municipality. Work included removing existing asphalt and disposing it together with constructing road layers which includes binder/wearing courses
The project consists of the construction, completion and maintenance of about 8 Km of roads in “King Hussein Bin Talal Economic Zone”. The Project also includes; construction of 2 Major roundabouts / Sidewalk / Median / Milling of existing asphalt / All earthwork necessary including structural excavation and backfill slope cutting / constructing all road layers (Topping, Sub base, Base, Wearing, Binder) / Construction of miscellaneous related work including protection , drainage, box curvets, retaining walls installation of new guardrail, curb stone, road signs and pavement marking
Asphalt work in various regions for Greater Amman Municipality. Work included removing existing asphalt and disposing it together with constructing road layers which includes binder/wearing courses
Excavation, Cut and Fill, and asphalt work for aircraft maintenance facility. The work also included supplying and application of bitumen seal, adding a special admixture to the asphalt in order to protect the asphalt from aircraft oil and chemicals
The project consists of development of the regions of the phosphate tunnel in terms of implementing new ways to link with Highway Amman - Zarqa in addition to the establishment of an overpass at the intersection of Al-Zarqa college with all the ways to link including “constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses / pavements (curbstone) / Drainage / Box curvets / Road electrical network / and Elements of traffic safety”.
(J.V Marwan Al-Kurdi and Partners & Al-Manhal Contracting Est.)
Asphalt work on Abdoun Suspension bridge.
Implementation of routine maintenance, preventive and emergency via military collage till Jabber boarders total length (( 62)) km
Asphalt work in various regions for Greater Amman Municipality. Work included removing existing asphalt and disposing it together with constructing road layers which includes binder/wearing courses
Asphalt work Q.A. Airport Work included removing existing asphalt and disposing it together with constructing road layers which includes binder/wearing courses
Asphalt work Marka Airport Work included removing existing asphalt and disposing it together with constructing road layers which includes binder/wearing courses
project consists of constructing service roads at the side of the existing road to hold the heavy traffic of the cement factory traffic. The Project construction work includes cut and fill work together with constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses.
The project consists of constructing 4.5 Km six carriageway road. The Project construction work includes cut and fill work together with constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses. Furthermore the project includes concrete works that is required for the curvets, box curvets and other miscellaneous work.
The project consists of constructing 28.5 Km road with average width of 1214- meters The Project construction work includes cut and fill work together with constructing road layers which includes; subgrade, granular sub-base, crushed aggregate base course and binder/wearing courses.
Furthermore the project includes concrete works that is required for the curvets, box curvets and other miscellaneous work.